Construction:

The following sequence of events and associated photos will provide an appreciation of what to expect in the construction of your new pool. Click on small photo to see larger version.

 1.  Establish the pool size and location working with Sam.

 2.  The pool outline will be marked with stakes and twine.

 3.  Excavation equipment will begin moving dirt from the pool and depositing the material into dump trucks located near your driveway.

 

 4.  Plumbing will be installed and structural steel will be put in place.

 5.  Gunite is "shot" onto the structural steel forming the pool's basic structure.

 

 6.  Tile and coping is installed.

 7.  Pool equipment is set.

 

 8.  Decking steel is installed and concrete is poured.

 9.  Plaster is used to cover the "water area" of the pool.

 

10. Final finish is installed on decking.

11. Pool is filled with water but not yet treated.

12. Two years after construction and landscaping by customer.